Just some random stuff from and about me
 
 

March

Posted at March 17, 2009 by The InsAnE Trash Can

Okay, okay! I’ve been slack updating my blog, so I should give an update of all the different tasks I’m doing and where I’m up to with them.

Tea Hedge

  • After planting the tea hedge it was realised that the area gets too wet and the plants would drown.
  • I’ve started building a small retaining wall around the hedge location so I can fill it with dirt and raise the tea plants above the pools of water that form.
  • I have installed 3 of the 3m sections and 1 of the 1 metre sections of the retaining wall.  I still have to install 2 more 3 metre sections and a 1 metre section.
  • After completing the retaining wall I will need to dig up all the tea plants and add approximately 4 or 5 cubic metres of soil.
  • To complete the retaining wall I had to purchase 22 x 3 metres sleepers, 52 x 150mm screws, 60 x 75mm screws, a chainsaw (to cut the sleepers) and a post-hole digger (’m not going to manually dig 600mm into pug soil).
  • I still need to adjust the over-flow pipe on my tank so It does not fill the tea hedge area.
  • The wall should be completed this Saturday (although I will not have the dirt by then).

Concrete Removal

  • The concrete removal hasn’t progressed much lately.
  • About 1/3rd of the concrete has been removed.
  • A further 1/3rd has been broken, ready to be removed.
  • I hope to have this done either Sunday this week or Saturday next week.

Ensuite

  • The ensuite is slowly progressing.
  • The electrician, unfortunately, found full-time work in the area and has not been able to do the wiring as yet.
  • After the electrician has done the wiring I will install the other half of the roof and the cement sheet walls.
  • I currently have the majority of parts to do the plumbing in the ensuite, this will be started as soon as possible.
  • I will begin with the waste-water pipes, then proceed to the cold water pipes.
  • Hot water installation will be combined with solar hot water installation.
  • Window frosting will be installed after I have painted the ensuite, which will happen after the cement sheet is installed.
  • Floor tiling will happen after the painting, and then I will just have to put everything in place.

Robe

  • I’ve worked out what color to do the robe.
  • I need to buy the wood to build the robe next.
  • I will do this after I have completed the ensuite.

Waste-water System

  • The waste-water system plans are currently with the council and should be approved this week.
  • The waste-water system will be installed once I have completed the backyard and ensuite.
 
Improve the web with Nofollow Reciprocity.
 
 
The Realm of the InsAnE Trash Can is powered by WordPress™ on FatMary Theme © 2008
‡ 14 queries in 0.422 sec ‡
 
 
 
 
Wall
 
Previous Next All
Latest on Wed, 23:10

Jazzy Nikita: Hey Bin - Hugs to you and Tonka :) Def have to catch up soon.

Ian Daniel: send me a email mike - it has been a really long time

Ian Daniel: Hey Mike - been a while, saying hi

Marc Jager: Hi Mike! Long time! Sounds like you are having a bit of stress lately! Grats on becoming a home-owner! You can still find me at marcjager.com [...]

bratty: ummmm sorry looks like the spud came with me niby :)

» Graffiti the wall!